Total Project Length: 74.98 km
Phase 1 Length: 38.111 km
Spur Lengths:
Bahadurgarh Spur: 7.269 km
Sonipat Spur: 29.60 km
Lanes: 6-lane main expressway & 4-lane spurs
Completion Deadline: December 2024
Estimated Cost: ₹7,715.60 crore
Right of Way (ROW): 100 meters
Owner: National Highway Authority of India (NHAI)
Status: Under Construction
Project Features and Route
Phase 1 Route:
Starts from NH-1 near Bankoli village and ends near Sector 24 in Dwarka.
It connects NH-1, NH-10, NH-8, and NH-2 via key regions including Bawana Industrial Area, Rohini, Mundka, Najafgarh, and Dwarka.Purpose:
Provides seamless access between north and northwest Delhi, IGI Airport, and Gurgaon.Engineering Model: EPC (Engineering, Procurement, and Construction).
Historical Background
Originally envisioned by Delhi Development Authority (DDA) under the Delhi Master Plan 2021, the project faced delays due to land acquisition and financial issues.
Handed over to NHAI in 2018, the project received ₹4,000 crore of viability gap funding from DDA.
Current Status
Expected Completion: December 2024.
Land Acquisition: Minor acquisitions underway.
Under Construction: 7.5 km stretch as part of Dwarka Expressway packages.
Tenders and Contractors
The project is divided into 5 packages:
Package Length Contractor Status Package 1 15.70 km HG Infra Engineering Under Construction Package 2 13.45 km Ceigall India – Krishna Constructions JV Under Construction Package 3 9.661 km Gawar Constructions Ltd. – ES Infra JV Under Construction Package 4 (Sonipat Spur) 29.60 km Ram Kumar Contractor Lowest Bidder, Work Assigned Package 5 (Bahadurgarh Spur) 7.269 km SS Builders – Diamond Construction JV Lowest Bidder, Work Assigned
Phase 2 of UER 2
The Delhi Government will take up Phase 2, which includes:
Rangpuri Bypass to Vasant Kunj.
Upgrades to Nelson Mandela Marg and Mehrauli-Badarpur Road.
Elevated corridors and interchanges at critical points.
Benefits of UER 2
Improved Connectivity: Seamless access across Delhi, Gurugram, and IGI Airport.
Decongestion: Reduces traffic pressure on NH-8 and other arterial roads.
Economic Boost: Facilitates trade and movement in Delhi NCR.
Environmental Advantage: Landscaping and greenery along the route for eco-friendliness.
Conclusion
The Delhi Urban Extension Road 2 (UER 2) is set to revolutionize connectivity across Delhi and neighboring regions. With its strategic route and integration with key highways, UER 2 will play a pivotal role in shaping the region's infrastructure and boosting economic growth. Stay tuned for updates as the project progresses toward its December 2024 completion!